Project results - July 2016

Written by  Thursday, 11 August 2016 12:43

 During the month of July continued the final part of the review of data concerning technical information mapped pylons - C1.

 

The plan of the conditions of planting and care of trees was created. They were contacted potential suppliers to determine the estimated cost as the basis for the procurement process, which will be implemented in August - C2.

 

At both locations - Hrhov also Gemerská Horka, continues to establish an appropriate management, largely removing shrubs and mowing. At both sites is continuing supplementary feeding populations affected by rains. - C5.

 

Sociological survey was conducted between mappers, focusing on basic demographic characteristics, motivation, experience, impressions, etc. The survey involved 62 mappers. The results was published on the project website in the News - D4.

 

Continues monitoring of the nesting success in project areas - D2.

Lucia Deutschová

manažérka projektu