Project results April - June 2019

Written by  Lucia Deutschová Monday, 12 August 2019 16:22

Installation for 22 kV is complete. The installation of the remaining 110 kV sections by VSD will continue as soon as possible, the installation is planned for the months August to September.

 

Checks of trees planted under the project and care were carried out.

 

A total of 9 birds were treated at UVLF.

 

All treated sections with flight diverters are regularly checked by monitoring the effectiveness in accordance with the D1 activity manual.

 

Monitoring and evaluation of nesting season continues.

 

Monitoring of the European ground squirells and the evaluation of the impact of project activities continues.

 

We organised one Press Conference with the cooperation of State Nature Conservancy and Západoslovenská ditribučná, a.s.
We recorded 22 media outputs.
Articles and data processing for the Slovak Raptor Journal are intensively developed.